Tuesday, September 27, 2011
North approach
Center. The contractor Ancon did the work of the curb cut along with
the concrete pad and walks. They also poured half of the approach on
the East side.
Tuesday, September 6, 2011
Final Documents
Pay Estimate 4 = $124,905.88
Pay Estimate 5 = $18,101.60
Final Change Order = $2,750.36 (Increase 0.77%)
Final Cost = $362,031.93
Monday, August 29, 2011
Approach issue
Tuesday, August 23, 2011
Payroll Issue
Wednesday, August 10, 2011
Payroll 1, 2, 3, 4, 5, 6, & 7
6/19/11
6/24/11
7/1/11
7/8/11
7/17/11
7/22/11
7/29/11
Payrolls 12, 13, 14, 15, 16, 17, & 18
6/20/11
6/27/11
7/4/11
7/11/11
7/18/11
7/25/11
8/1/11
Payroll 1
Friday, August 5, 2011
Daily 8/5
Thursday, August 4, 2011
Monday, August 1, 2011
Daily 8/1
Mike
Friday, July 29, 2011
Daily 7/29
Mike
Thursday, July 28, 2011
Daily 7/28
the two handholes (change order) and will be replacing the lids. They
say traffic signs instead of fiber.
Mike
Wednesday, July 27, 2011
Daily 7/27
Tuesday, July 26, 2011
Daily 7/26
needs to be milled and resurfaced. Meeting is set for 7/27 9:30 am on
site with Thad, Less, Toy and myself.
Mike
Monday, July 25, 2011
Daily 7/25
it and agreed that it is not acceptable. Contacted Thad to inform him
that the surface will have to milled and resurfaced.
Sunday, July 24, 2011
Daily Reports Trade Dr
Tuesday, July 12, 2011
Construction notes
W&K - 1 F/3 Op/2 Lab. Gradeall, roller, grader
Prep subgrade, place asphalt on EB section of Lathrop
Michiana Contracting - 1 F/ 2 Sign Tech. Small backhoe
Place conduit on east side of Trade Dr and light base on NW for Lathrop & Trade Dr
07/12/11
W&K - 1 F/ 3 Op/ 3. Lab. Backhoe, paver, 2 roller
Place base on entire area
Michiana - 1 F/ 2 Sign Tech. Small backhoe
Continue placement of conduit for lights around cul-de-sac.
Thia Vawter
Project Inspector
Friday, July 8, 2011
Thursday, July 7, 2011
Wednesday, July 6, 2011
Daily 7/6
"Not hot old line".
Walsh & Kelly started the day placing string line for the curb and
started to pour around 11:30 with a total of seven truck on order.
Tuesday, July 5, 2011
Daily 7/5
Still no word on how the cable shown in the picture was cut. Now there
is a red tag attached to cable as shown.
Met with Jared an Les from Walsh & Kelly on site to discuss the curb
and concrete work. Crews will show up later today to set string.
Wednesday and Thursday crew will place the concrete work
Friday, July 1, 2011
Daily 7/1
Met with Thad on site to discuss the type of curb returning. On the south side of Lathrop it is going to be type A curb and gutter (rolled curb) to match existing. On trade drive it will be type B curb and gutter.
There is an issue with an underground cable on the East side of the private drive. It was not marked when locates where done at the start of the project. It has been discovered it was cut today. C&E claimed they did not do it as well as Walsh & Kelly. It is predicted that the line is a dead line. Thad is going to have the locater person determine if it is an active line in the near future.
Pay Estimate 3
Thursday, June 30, 2011
Wednesday, June 29, 2011
Tuesday, June 28, 2011
Monday, June 27, 2011
Friday, June 24, 2011
Thursday, June 23, 2011
Daily 6/23
Mike
4302 Lathrop
Their business is located at 4302 Lathrop. Every since the construction project out there between their business and UPS, their parking lot has flooded. She is not sure who she should contact. Thank you.
Wednesday, June 22, 2011
Daily 6/22
Crews ready to lay the stone but because of the Local 150 strike Walsh
and Kelly were going to do it but C&E will do. They could lay stone
today because they ran out of material.
Tuesday, June 21, 2011
Daily 6/21
Crews are also adjusting the remaining casting and general site clean up.
Water testing being done today.
Monday, June 20, 2011
Payrolls No 8, 9, 10 & 11
5/23/11
5/30/11
6/6/11
6/13/11
Daily 6/20
65' and 32' remaining pipe
Mike
Friday, June 17, 2011
Daily 6/17
Crews on site grading the remaining part of the road.
Crews scheduled mud today to finish the two inlets.
Crews are also going to finish the fence at the airport.
Fwd: Jobs involving Walsh & Kelly, Inc.
From: Michael Carey <mbcarey@southbendin.gov>
Date: June 17, 2011 8:30:16 AM EDT
To: Thad Bessinger <Tbessinger@candeexcavating.com>
Subject: Re: FW: Jobs involving Walsh & Kelly, Inc.
ThadI am aware of the Local 150 strike that occurred on June 13th, 2011. 2010 INDOT Standard Specification section 108.08 line 420 states excusable delays and I am more than willing to work with you to track the days. If you have any questions call or email me.ThanksMike
--Michael CareyEngineer InspectorCity of South Bend Engineer Dept.Suite 1316, County/City Bldg.227 West Jefferson Blvd.South Bend, IN 46601C: 574-387-6404O: 574-235-5896F: 574-235-9171On Mon, Jun 13, 2011 at 2:11 PM, Mike B. Carey <MBCAREY@webmaster@southbendin.gov> wrote:
Mike,
Please see below on Local 150 strike. We are requesting time extension to deal with this strike that is out of our control. I expect, weather permitting we will be done a trade until Walsh & Kelly installs the stone base, curb and asphalt.
Thanks
Thad Bessinger
Vice-President
C&E Excavating, Inc.
53767 CR9 Elkhart, IN 46514
Phone:(574)262-4346
Fax:(574)262-9251
Cell:(574)536-0801
From: Les Heiser [mailto:LesH@Walshkelly.com]
Sent: Monday, June 13, 2011 2:05 PM
To: Davidwalorski@cs.com; Thad Bessinger; Calvin Roach
Subject: Jobs involving Walsh & Kelly, Inc.
Dear Sir, Possibly you already know that this morning, June 13, 2001, the Operating Engineers went on strike at our facilities. Pickets were set up in front of Walsh & Kelly, Inc., Rieth-Riley, E&B, Phend & Brown and I assume other union asphalt plants. This strike affects all our operations. The word is that the number of pickets will increase tomorrow to include job sites. We at Walsh & Kelly, Inc. are essentially shut down. The work stoppage is for all contracts under the 4 county and 10 county agreements which covers St. Joseph and Elkhart Counties. Per Section 108.08 line 331 of the 2010 INDOT Standard Specifications we are requesting additional time as necessary during this work stoppage for completion of the work on the specific contract we have with you. I will keep you updated. As of this date we have no idea how long this will last. Please schedule accordingly realizing that at some point, if not immediately, this strike will affect your controlling operation. Please pass this information on to all affected parties regarding work Walsh & Kelly, Inc. is to perform. Sincerely, Walsh & Kelly, Inc., Les Heiser, Project Engineer
IMPORTANT NOTICE! This E-Mail transmission and any accompanying attachments may contain confidential information intended only for the use of the individual or entity named above. Any dissemination, distribution, copying or action taken in reliance on the contents of this E-Mail by anyone other than the intended recipient is strictly prohibited and is not intended to, in anyway, waive privilege or confidentiality. If you have received this E-Mail in error please immediately delete it and notify sender at the above E-Mail address.
Thursday, June 16, 2011
Daily 6/16
Strs today or tomorrow.
The other crew is peeping the drives on the East side. Finished the
south one and going to complete the north one along with 6" concrete
pad.
Wednesday, June 15, 2011
Tuesday, June 14, 2011
Monday, June 13, 2011
Daily 6/13
that the drive that was taken out on the south side of Lathrop, the
curb needs to be installed in place of the block curb.
The other crew finished installing the water main and second fire hydrant.