Tuesday, 07/12/11 Sunny L 68 H 84
C&E - 1 Op - Backhoe
W&K - 1 F/ 3 Op / 3 Lab, paver, roller, sweeper
Muchiana Contracting - 1F / 2 Sig Tech
C&E - Backfilling curbs and partial de mob
W&K - Pave base and intermediate. SB plant had a breakdown, five trucks of mix came from Goshen plant. Same mix as approved - INDOT.
Michiana - Place conduit and junction boxes.
Wednesday, 07/13/11 Sunny L 66 H 75
W&K - 1 F / 3 Op / 2 Lab
Pave remaining Intermediate and surface
Thursday, 07/14/11 Sunny L62 H 83
Michiana - 1 F / 2 Sig Tech
Set 2 F/O handholes
Place concrete around junction boxes
C&E - De mob
**Checked finish surface - looks terrible - roller marks, dips, exposed aggregate, areas os separation. Met w/Jason (C&E) & Les (W&K) - Jason not pleased. Les said he would have to have Dustin Hillary look at it and decide what to do about it. I told him that it should all be milled up and redone, but +/- 75% is ok. Les will get back with me as soon as he and Dustin look at it.
Friday, 0722/11 Cloudy/Rain pm L 73 H 86
Talked to Dustin - He said that W&K rerolled the entire area on Trade Dr and he thought it did some good. I told him I would go and look at it on Monday and determine if the entire surface has to milled.
No comments: