The NTP issued for April 4, 2011.
Project completion Date is August 19, 2011
Wednesday, March 30, 2011
Tuesday, March 29, 2011
Pre-Con
Trade Drive
Project No.: 110-048
Pre-Construction Meeting – March 30, 2011
13th Floor County-City Building – Engineering Conference Room
Introductions – Sign in Sheet
1. Roles:
a. OWNER – City of South Bend
b. CONTRACTOR – C & E Excavating
c. ENGINEER / CONSTRUCTION OBSERVATION – Mike Carey
2. Contacts (list from contractor)
Bonding Requirements
1. Maintenance Bond required
Wage Rates
1. Schedule of Wages from C & E Excavating from all Sub-contractors (on letterhead)
2. Certified Payroll every 2 weeks
Submittals
1. 7 hard copies – review and return 2 copies. (If required)
Notice To Proceed
1. To be issued April 4, 2011
Prosecution & Progress
1. Final Completion – July 1, 2011
2. Maintain access to all adjacent properties during construction
3. Provide Schedule prior to starting of construction – If required
Change of Contract Time
1. Contract time may only be changed by an approved Change Order.
Liquidated Damages
1. $2,500 / calendar day past the final completion date
Retainage and Final Payment
1. Payment Application every 30 days
2. 5% Retainage
3. Final Payment and Release of Retainage requires submittal of waiver of lien, completion affidavit, as-builts showing utilities capped and a conformed set of submittals (If required).
Testing
1. Compaction Testing
Maintenance of Traffic
1. Traffic Control Plan (If required)
Mobilization and Demobilization
1. Mobilization – 75%
2. Demobilization – 25% upon completion
Erosion Control
1. Weekly self inspections / inspections after rain events.
HMA Patching
1. Contractor is responsible for testing.
2. Mix Design Submittal
Dewatering
1. If dewatering is required it will be considered incidental.
2. Contractor to provide a dewatering plan to the City for review.
Borrow Material for Backfill
1. Borrow material shall be a clean sand or sand and gravel free of roots.
Topsoil & Seeding
1. Contractor responsible for hydro-seeding.
2. Topsoil – testing requirements / pre-approval before placement
Questions / Comments
- Borrow material can be excess material on-site
- Borrow material can be from a pit on the Airport's property
- Borrow material can be from pit close to C & E property
- Michiana Contracting - Electrical
- Peaks - Tree clearing (Donna)
Monday, March 28, 2011
Friday, March 11, 2011
C&E Request to Start
Rob and Toy,
Thad Bessinger emailed me to see if C&E could start on Trade Dr? So I wanted to check with you guys since I was not sure on the status.
Thanks,
Brian M. Smith, P.E., LEED AP
Project Manager
DLZ Indiana, LLC
Gentlemen:
Mike has looked into the contract being submitted and C & E has not submitted their signed contracts for Board approval. Therefore we cannot hold a pre-con meeting nor provide a notice to proceed on the project. One would only think that Thad should know better then to ask for a pre-con.
We will move forward when the Board has the contract in hand and approved.
We will move forward when the Board has the contract in hand and approved.
Regards,
Toy
Toy Villa
Manager
Bureau of Public Construction
(574)235-5920
Subscribe to: