Pre-Con

Trade Drive
Project No.:  110-048

Pre-Construction Meeting – March 30, 2011
13th Floor County-City Building – Engineering Conference Room

Introductions – Sign in Sheet
1.       Roles:
a.       OWNER – City of South Bend
b.      CONTRACTOR – C & E Excavating
c.       ENGINEER / CONSTRUCTION OBSERVATION – Mike Carey
2.       Contacts (list from contractor)

Bonding Requirements
1.       Maintenance Bond required

Wage Rates
1.       Schedule of Wages from C & E Excavating from all Sub-contractors (on letterhead)
2.       Certified Payroll every 2 weeks

Submittals
1.       7 hard copies – review and return 2 copies. (If required)

Notice To Proceed
1.   To be issued April 4, 2011

Prosecution & Progress
1.       Final Completion – July 1, 2011
2.       Maintain access to all adjacent properties during construction
3.       Provide Schedule prior to starting of construction – If required

Change of Contract Time
1.       Contract time may only be changed by an approved Change Order.

Liquidated Damages
1.       $2,500 / calendar day past the final completion date

Retainage and Final Payment
1.       Payment Application every 30 days
2.       5% Retainage
3.       Final Payment and Release of Retainage requires submittal of waiver of lien, completion affidavit, as-builts showing utilities capped and a conformed set of submittals (If required).

Testing
1.       Compaction Testing

Maintenance of Traffic
1.       Traffic Control Plan (If required)

Mobilization and Demobilization
1.       Mobilization – 75%
2.       Demobilization – 25% upon completion

Erosion Control
1.       Weekly self inspections / inspections after rain events.

HMA Patching
1.       Contractor is responsible for testing.
2.       Mix Design Submittal

Dewatering
1.   If dewatering is required it will be considered incidental.
2.   Contractor to provide a dewatering plan to the City for review.

Borrow Material for Backfill
1.       Borrow material shall be a clean sand or sand and gravel free of roots.

Topsoil & Seeding
1.       Contractor responsible for hydro-seeding.
2.       Topsoil – testing requirements / pre-approval before placement

Questions / Comments
  • Borrow material can be excess material on-site
  • Borrow material can be from a pit on the Airport's property
  • Borrow material can be from pit close to C & E property
  • Michiana Contracting - Electrical
  • Peaks - Tree clearing (Donna)