ARS on site working on the area of problem on the asphalt.
Mike
Friday, July 29, 2011
Thursday, July 28, 2011
Daily 7/28
No Work. Took measurements. Dave Delp will be looking at the price for
the two handholes (change order) and will be replacing the lids. They
say traffic signs instead of fiber.
the two handholes (change order) and will be replacing the lids. They
say traffic signs instead of fiber.
Mike
Wednesday, July 27, 2011
Daily 7/27
Met with Thad, Less, Toy and myself on site about the issue of the surface asphalt. It was discussed that the leg is OK and the cul-de-sac should be milled and resurfaced. Less from Walsh and Kelly did apologize for the condition of the surface. He did urged to use a sand component to "fix" the bad spots. He will get back with us on what method will be used.
Tuesday, July 26, 2011
Daily 7/26
Met with Toy, Thia, and myself on site. Toy agreed that the asphalt
needs to be milled and resurfaced. Meeting is set for 7/27 9:30 am on
site with Thad, Less, Toy and myself.
needs to be milled and resurfaced. Meeting is set for 7/27 9:30 am on
site with Thad, Less, Toy and myself.
Mike
Monday, July 25, 2011
Daily 7/25
No work today but issues with the asphalt. Thia and myself looked at
it and agreed that it is not acceptable. Contacted Thad to inform him
that the surface will have to milled and resurfaced.
it and agreed that it is not acceptable. Contacted Thad to inform him
that the surface will have to milled and resurfaced.
Sunday, July 24, 2011
Daily Reports Trade Dr
Tuesday, 07/12/11 Sunny L 68 H 84
C&E - 1 Op - Backhoe
W&K - 1 F/ 3 Op / 3 Lab, paver, roller, sweeper
Muchiana Contracting - 1F / 2 Sig Tech
C&E - Backfilling curbs and partial de mob
W&K - Pave base and intermediate. SB plant had a breakdown, five trucks of mix came from Goshen plant. Same mix as approved - INDOT.
Michiana - Place conduit and junction boxes.
Wednesday, 07/13/11 Sunny L 66 H 75
W&K - 1 F / 3 Op / 2 Lab
Pave remaining Intermediate and surface
Thursday, 07/14/11 Sunny L62 H 83
Michiana - 1 F / 2 Sig Tech
Set 2 F/O handholes
Place concrete around junction boxes
C&E - De mob
**Checked finish surface - looks terrible - roller marks, dips, exposed aggregate, areas os separation. Met w/Jason (C&E) & Les (W&K) - Jason not pleased. Les said he would have to have Dustin Hillary look at it and decide what to do about it. I told him that it should all be milled up and redone, but +/- 75% is ok. Les will get back with me as soon as he and Dustin look at it.
Friday, 0722/11 Cloudy/Rain pm L 73 H 86
Talked to Dustin - He said that W&K rerolled the entire area on Trade Dr and he thought it did some good. I told him I would go and look at it on Monday and determine if the entire surface has to milled.
Tuesday, July 12, 2011
Construction notes
07/11/11
W&K - 1 F/3 Op/2 Lab. Gradeall, roller, grader
Prep subgrade, place asphalt on EB section of Lathrop
Michiana Contracting - 1 F/ 2 Sign Tech. Small backhoe
Place conduit on east side of Trade Dr and light base on NW for Lathrop & Trade Dr
07/12/11
W&K - 1 F/ 3 Op/ 3. Lab. Backhoe, paver, 2 roller
Place base on entire area
Michiana - 1 F/ 2 Sign Tech. Small backhoe
Continue placement of conduit for lights around cul-de-sac.
Thia Vawter
Project Inspector
W&K - 1 F/3 Op/2 Lab. Gradeall, roller, grader
Prep subgrade, place asphalt on EB section of Lathrop
Michiana Contracting - 1 F/ 2 Sign Tech. Small backhoe
Place conduit on east side of Trade Dr and light base on NW for Lathrop & Trade Dr
07/12/11
W&K - 1 F/ 3 Op/ 3. Lab. Backhoe, paver, 2 roller
Place base on entire area
Michiana - 1 F/ 2 Sign Tech. Small backhoe
Continue placement of conduit for lights around cul-de-sac.
Thia Vawter
Project Inspector
Friday, July 8, 2011
Thursday, July 7, 2011
Wednesday, July 6, 2011
Daily 7/6
The red tag that was discovered yesterday on the back side it says
"Not hot old line".
Walsh & Kelly started the day placing string line for the curb and
started to pour around 11:30 with a total of seven truck on order.
"Not hot old line".
Walsh & Kelly started the day placing string line for the curb and
started to pour around 11:30 with a total of seven truck on order.
Tuesday, July 5, 2011
Daily 7/5
Ancon tapped into the sewer lateral.
Still no word on how the cable shown in the picture was cut. Now there
is a red tag attached to cable as shown.
Met with Jared an Les from Walsh & Kelly on site to discuss the curb
and concrete work. Crews will show up later today to set string.
Wednesday and Thursday crew will place the concrete work
Still no word on how the cable shown in the picture was cut. Now there
is a red tag attached to cable as shown.
Met with Jared an Les from Walsh & Kelly on site to discuss the curb
and concrete work. Crews will show up later today to set string.
Wednesday and Thursday crew will place the concrete work
Friday, July 1, 2011
Daily 7/1
No work today due to rain showers in the late morning and afternoon.
Met with Thad on site to discuss the type of curb returning. On the south side of Lathrop it is going to be type A curb and gutter (rolled curb) to match existing. On trade drive it will be type B curb and gutter.
There is an issue with an underground cable on the East side of the private drive. It was not marked when locates where done at the start of the project. It has been discovered it was cut today. C&E claimed they did not do it as well as Walsh & Kelly. It is predicted that the line is a dead line. Thad is going to have the locater person determine if it is an active line in the near future.
Met with Thad on site to discuss the type of curb returning. On the south side of Lathrop it is going to be type A curb and gutter (rolled curb) to match existing. On trade drive it will be type B curb and gutter.
There is an issue with an underground cable on the East side of the private drive. It was not marked when locates where done at the start of the project. It has been discovered it was cut today. C&E claimed they did not do it as well as Walsh & Kelly. It is predicted that the line is a dead line. Thad is going to have the locater person determine if it is an active line in the near future.
Pay Estimate 3
Approved pay estimate 3 with the amount of $82,980.83 with a running total of $219,024.46