Thursday, June 30, 2011
Wednesday, June 29, 2011
Tuesday, June 28, 2011
Monday, June 27, 2011
Friday, June 24, 2011
Thursday, June 23, 2011
Daily 6/23
Mike
4302 Lathrop
Their business is located at 4302 Lathrop. Every since the construction project out there between their business and UPS, their parking lot has flooded. She is not sure who she should contact. Thank you.
Wednesday, June 22, 2011
Daily 6/22
Crews ready to lay the stone but because of the Local 150 strike Walsh
and Kelly were going to do it but C&E will do. They could lay stone
today because they ran out of material.
Tuesday, June 21, 2011
Daily 6/21
Crews are also adjusting the remaining casting and general site clean up.
Water testing being done today.
Monday, June 20, 2011
Payrolls No 8, 9, 10 & 11
5/23/11
5/30/11
6/6/11
6/13/11
Daily 6/20
65' and 32' remaining pipe
Mike
Friday, June 17, 2011
Daily 6/17
Crews on site grading the remaining part of the road.
Crews scheduled mud today to finish the two inlets.
Crews are also going to finish the fence at the airport.
Fwd: Jobs involving Walsh & Kelly, Inc.
From: Michael Carey <mbcarey@southbendin.gov>
Date: June 17, 2011 8:30:16 AM EDT
To: Thad Bessinger <Tbessinger@candeexcavating.com>
Subject: Re: FW: Jobs involving Walsh & Kelly, Inc.
ThadI am aware of the Local 150 strike that occurred on June 13th, 2011. 2010 INDOT Standard Specification section 108.08 line 420 states excusable delays and I am more than willing to work with you to track the days. If you have any questions call or email me.ThanksMike
--Michael CareyEngineer InspectorCity of South Bend Engineer Dept.Suite 1316, County/City Bldg.227 West Jefferson Blvd.South Bend, IN 46601C: 574-387-6404O: 574-235-5896F: 574-235-9171On Mon, Jun 13, 2011 at 2:11 PM, Mike B. Carey <MBCAREY@webmaster@southbendin.gov> wrote:
Mike,
Please see below on Local 150 strike. We are requesting time extension to deal with this strike that is out of our control. I expect, weather permitting we will be done a trade until Walsh & Kelly installs the stone base, curb and asphalt.
Thanks
Thad Bessinger
Vice-President
C&E Excavating, Inc.
53767 CR9 Elkhart, IN 46514
Phone:(574)262-4346
Fax:(574)262-9251
Cell:(574)536-0801
From: Les Heiser [mailto:LesH@Walshkelly.com]
Sent: Monday, June 13, 2011 2:05 PM
To: Davidwalorski@cs.com; Thad Bessinger; Calvin Roach
Subject: Jobs involving Walsh & Kelly, Inc.
Dear Sir, Possibly you already know that this morning, June 13, 2001, the Operating Engineers went on strike at our facilities. Pickets were set up in front of Walsh & Kelly, Inc., Rieth-Riley, E&B, Phend & Brown and I assume other union asphalt plants. This strike affects all our operations. The word is that the number of pickets will increase tomorrow to include job sites. We at Walsh & Kelly, Inc. are essentially shut down. The work stoppage is for all contracts under the 4 county and 10 county agreements which covers St. Joseph and Elkhart Counties. Per Section 108.08 line 331 of the 2010 INDOT Standard Specifications we are requesting additional time as necessary during this work stoppage for completion of the work on the specific contract we have with you. I will keep you updated. As of this date we have no idea how long this will last. Please schedule accordingly realizing that at some point, if not immediately, this strike will affect your controlling operation. Please pass this information on to all affected parties regarding work Walsh & Kelly, Inc. is to perform. Sincerely, Walsh & Kelly, Inc., Les Heiser, Project Engineer
IMPORTANT NOTICE! This E-Mail transmission and any accompanying attachments may contain confidential information intended only for the use of the individual or entity named above. Any dissemination, distribution, copying or action taken in reliance on the contents of this E-Mail by anyone other than the intended recipient is strictly prohibited and is not intended to, in anyway, waive privilege or confidentiality. If you have received this E-Mail in error please immediately delete it and notify sender at the above E-Mail address.
Thursday, June 16, 2011
Daily 6/16
Strs today or tomorrow.
The other crew is peeping the drives on the East side. Finished the
south one and going to complete the north one along with 6" concrete
pad.
Wednesday, June 15, 2011
Tuesday, June 14, 2011
Monday, June 13, 2011
Daily 6/13
that the drive that was taken out on the south side of Lathrop, the
curb needs to be installed in place of the block curb.
The other crew finished installing the water main and second fire hydrant.
Friday, June 10, 2011
Thursday, June 9, 2011
Shop Drawings
Wednesday, June 8, 2011
Erosion control reports
Tuesday, June 7, 2011
Monday, June 6, 2011
Daily 6/6
Beginning to lay the remaining 18" RCP from Str 15 to Str 12.
It was discovered today that the electrical plans called for 1 1/2" conduit for the street lights on the project. I was informed by the designer DLZ that the reasoning for 1 1/2" conduit was that it could fit up to 7 #4 wires but the specs call for only 4 #4 wires. The standard for the city is 2" and informed the contractor to use the 2" in place of the 1 1/2" and there is no need to give a price because there is a line item for the 2" PVC conduit.
Friday, June 3, 2011
Thursday, June 2, 2011
Daily 6/2
issues at a different job down the road.
Wednesday, June 1, 2011
Daily 6/1
hydrant water service.
Mike's Fencing finished the fence at the airport at 8pm last night.
C&E is to finish the base of the fence with the stone.