Finished laying 8" PVC SDR 35 to Str 502, 201 Lt total. Crews will
work in the storm pipe next.
Mike's fencing on site to finishing completing the fence at the airport.
Tuesday, May 31, 2011
Friday, May 27, 2011
Daily 5/27
Crews laying 8" PVC from Str 501 to 502.
Ian contacted Mikes fencing and they are planning to be out Tuesday.
3 Sticks of water main total of 54 ft
Ian contacted Mikes fencing and they are planning to be out Tuesday.
3 Sticks of water main total of 54 ft
9 sticks 8" PVC from Str 501 to Str 502
3 Sticks of water main total of 54 ft
3 Sticks of water main total of 54 ft
3 Sticks of water main total of 54 ftsticks 8" PVC from Str 501 to Str 502
3 Sticks of water main total of 54 ft
Thursday, May 26, 2011
Daily 5/26
No work due to rain showers in the forecast.
Mike
Payrolls No 5, 6, & 7
Approved and filed the payrolls for the weeks ending in:
5/2/11
5/9/11
5/16/11
5/2/11
5/9/11
5/16/11
Wednesday, May 25, 2011
Daily 5/25
No work due to thunderstorms on and off today.
Tuesday, May 24, 2011
Monday, May 23, 2011
Daily 5/23
Measure 272 LF from Str 500 to 501. Shown in picture is Str 501.
Crews continue to lay 24" RCP fro
Str 16.
Crews continue to lay 24" RCP fro
Str 16.
Friday, May 20, 2011
Daily 5/20
Crews placed the 8" PVC to the East about 8"-10" away from the new lateral.
Placed Str 501 and 8" PVC.
Placed Str 501 and 8" PVC.
Daily 5/20
Contact Jack from Ancon about the sewer lateral from the building.
Location is correct, the manhole is moving about 11' south. Elevations
of the buildings lateral will be very close to grade to prints.
Confirmed the numbers with Ty and they are going to make it work.
Crews plan on laying pipe to Str 501, setting Str 501 and laying the
stub to the East.
Asked the crew to remove the one lane and shift right/left signs for
the weekend.
Location is correct, the manhole is moving about 11' south. Elevations
of the buildings lateral will be very close to grade to prints.
Confirmed the numbers with Ty and they are going to make it work.
Crews plan on laying pipe to Str 501, setting Str 501 and laying the
stub to the East.
Asked the crew to remove the one lane and shift right/left signs for
the weekend.
Voicemail from (574) 971-6738 at 8:16 AM
Contacted Jack the Ancon foreman to verify the location of the sewer lateral.
Mike
Mike
Begin forwarded message:
From: Google Voice <voice-noreply@google.com>
Date: May 20, 2011 8:18:30 AM EDT
To: MBCareyatWork@gmail.com
Subject: New voicemail from (574) 971-6738 at 8:16 AM
Voicemail from: (574) 971-6738 at 8:16 AM Hey Mike, My name is Jack while around with Bangkok construction I understand you stopped out the That's the job site yesterday, why I was gone. If you want to give me a call. My number is 574971673 day. That was a joke Correctional Center. So, gimme a call. Thank you.
Play message
Thursday, May 19, 2011
Daily 5/19
Crews are continuing laying 8" PVC sanitary pipe.
Str 501 might have to be moved 11 feet to the south. But looking at
the stakes and the cleanout at the building it could be that it is in
the correct spot. Will be contacted by the foreman from the building
to get conformation.
Str 501 might have to be moved 11 feet to the south. But looking at
the stakes and the cleanout at the building it could be that it is in
the correct spot. Will be contacted by the foreman from the building
to get conformation.
Wednesday, May 18, 2011
Daily 5/18
Crews have installed water main and sanitary pipe the day before to extend beyond the road.
Crews are compacting the base for the road and laying 53's for the temporary road that has to be open for the weekend. Notre Dame is having graduation this weekend and there is expected to be large traffic amounts from Atlantic Avaition.
There is an issue with the placement of th sanitary manhole. The location of the building's recently placed stub is about 11 to the south. C&E with install the manhole at the location of the stub in turn shorting the south side pipe from 288' to 277' and the North side longer from 193' to 204'.
Cal-Pro is to be providing a schedule for the fence replacement.
Contacted the general manger at Atlantic Avaition with an issue regarding an email forward to me regarding the condition of the road I told her stone is in the road and will be open to two lanes by today or tomorrow.
Tuesday, May 17, 2011
Daily 5/17
Hoe packing base.
Installed valve box.
Installed watermain.
All work done above is in the area for prepping the sub base for
pavement at the South side of Lathrop Dr.
Installed valve box.
Installed watermain.
All work done above is in the area for prepping the sub base for
pavement at the South side of Lathrop Dr.
Pay Estimate 1
Submitted pay estimate 1 for 4/4/11 to 4/30/11 in the amount of $69,627.69.
Monday, May 16, 2011
Daily 5/16
Complaint this morning due to the condition of the road and the condition of the fence. John Schallo was the person in contact at the airport. Thad at C&E was informed of the problems as well.
Over the weekend the city received over 2" of rain. The temporary road was very muddy this morning. It was insisted the road be open this weekend for ND graduation.
A fence contractor was informed about the fence and the fence will be repaired ASAP and the remaining work such as replacing the road and the installation of the casting.
Thad asked about the pay estimate again and I contacted Andy from soil and water about having to correct paperwork on site.
Over the weekend the city received over 2" of rain. The temporary road was very muddy this morning. It was insisted the road be open this weekend for ND graduation.
A fence contractor was informed about the fence and the fence will be repaired ASAP and the remaining work such as replacing the road and the installation of the casting.
Thad asked about the pay estimate again and I contacted Andy from soil and water about having to correct paperwork on site.
Friday, May 13, 2011
Daily 5/13
Crews are laying pipe in the area of the road. Traffic is diverted to
a one lane just North of the existing road.
At the end of the day the crews backfilled the south side of the road
and opened it up for traffic. Crews had to work fast because of the
rain storm that started around 4:00 pm.
a one lane just North of the existing road.
At the end of the day the crews backfilled the south side of the road
and opened it up for traffic. Crews had to work fast because of the
rain storm that started around 4:00 pm.
Thursday, May 12, 2011
Daily 5/12
Starting to lay 8" sanitary from Str 500.
The road is down to one lane on stone. Asked Ian to install a one lane sign.
The road is down to one lane on stone. Asked Ian to install a one lane sign.
Wednesday, May 11, 2011
Trade Drive, Soil & Water Inspection
Andrew,
I am the Estimator/Project manager for C&E Excavating on the Trade Drive project. I just received your on-site evaluation in the mail this morning. I spoke to my foreman Ian Mundy and he was surprised at the report, he claims he talked to you last Friday 5/6/11 onsite and you told him everything looked good. If we had known of any issues we would have addressed them sooner as we know how important they are to you and most especially the city of South Bend. Please in the future if there is something you notice of concern don’t hesitate to talk directly to Ian or any of my onsite foremen regardless of the project. Below is our current plan of attack on your issues. Please feel free to comment if there is anything you want done differently.
1.)The tracking of dirt. We have been cleaning soil off of Lathrop at the end of each day and if it gets bad, during the day. The #2’s were installed Monday following your inspection to help deal with this issue. We currently removing the roadway to install sewer and water, so we will have to remain vigilant in the cleaning of the street and maintenance of this stone as we cross the roadway and re-direct traffic flow.
We have installed silt fence around the topsoil and southwest section of the project as of this morning.
We intend on permanent seeding the area disturbed as soon as we are done in those areas. The final grade isn’t entirely complete. We have castings to adjust to grade and a roadway to install at the north end of the site before completing the final grading.
I will be speaking to Mike Carey my inspector about the other issues and how to get them addressed asap. If he approves it should I copy you on all my weekly site inspection reports? I believe he keeps them on file.
Thanks
Thad Bessinger
Thad,
I must apologize to Mr. Mundy. Everything was pretty much in order as we discussed on site. As I was leaving though I happen to notice the couple of small issues, and I did not see Mr. Mundy around to make him aware of these issues.
The installed silt fence on the southwest side should take care of any erosion from the stock piles, especially if the whole field in this area is on the project property. Also, as long as the street sweeping is taking place, and you have the documentation for this activity, everything should be fine. You do not need to send me your self-inspection reports every week, but please send at least a summary of the ones you have on file up to the date of my inspection. Along with these reports please also include any off site sedimentation prevent measures taken (i.e. street sweeping).
I did mention in my evaluation that there are areas which needed to be permanently seeded, but this is mostly to help in my future inspections, and to serve as a reminder for the future for you. I recall speaking to Mr. Mundy and he had mentioned that he had just finished the grading of the area adjacent to the outlet structure a day or so before my inspection. He also mentioned that he would be scheduling a seeding of that area in the near future, which is fine.
The only other item that needs to be addressed was that of posting the required information at the construction site.
Overall it sounds and looks as if your crew has been doing a great job! Other than these few minor items, which is sounds like you have a good handle on taking care of already, keep up the good work.
Thanks,
Andrew S. Fox
Daily 5/11
Received an issue with erosion control plan at the site. Thad was
contacted by Andrew with Soil & Water. Issue with silt fence, dirt on
the road, and construction entrance. As of this morning, they
corrected the issue.
contacted by Andrew with Soil & Water. Issue with silt fence, dirt on
the road, and construction entrance. As of this morning, they
corrected the issue.
Payrolls 3 & 4
Approved and filed payrolls for the weeks ending 4/18/11 and 4/25/11
Tuesday, May 10, 2011
Daily 5/10
Excavated material to place the box. The box was placed under an AT&T conduit and AEP conduit (left of the box in the picture).
Exposed the water main located in the road.
Contacted Dave from Michigan Contracting regarding the submittal of the electrical light poles. The issue was that the model number of the poles is not the same as defined in the specs. He is going to send me something that states from the manufacturer the Hapco pole is the same as the Spaulding pole stated in the plans and specs.
Monday, May 9, 2011
Daily 5/9
Removal of drive way begins, and traffic control placed. Encountered an underground service that was not marked, it ran at the under the curb in the driveway.
Friday, May 6, 2011
Daily 5/6
Prep to remove road. Saw cut to remove asphalt. The plans called to remove 8 feet from curb on the driveway. Ian suggested removal of more road was need because the depth of the manhole (17'), he felt that the remaining asphalt driveway would under mind because of the depth. I gave him the OK to remove the remaining driveway.
Crews continued removal for the road (Trade Dr.)