Friday, April 29, 2011

Daily 4/29

Crews continue to lay 24" RCP storm to Str 16.

Mix Design

Approved mix designs for
Walsh & Kelly asphalt base, base/binder, and surface



Walsh & Kelly concrete curb and sidewalk/approach

Thursday, April 28, 2011

Daily 4/28

Installation of storm pipe continues after three days off this week
due to persistent rains. Site is a bit muddy.

Wednesday, April 27, 2011

Tuesday, April 26, 2011

Monday, April 25, 2011

Daily 4/25

No work due to rain. The conditions at the site are unsuitable for excavating.

Friday, April 22, 2011

Thursday, April 21, 2011

Daily 4/21

Storm pipe continues. Running into issues of mud. It appears to just
be slowing down the process.

Site Inspection Report 4/15

Received the first site inspection report from Thad B.

Wednesday, April 20, 2011

Daily 4/20

Storm pipe installation continues with the addition of a manhole. Site
was a little muddy due the past two days of rain.

Tuesday, April 19, 2011

Monday, April 18, 2011

Payrolls No 1 & 2

Approved and filed the payrolls for the week ending 4/4/11 and 4/11/11.

Daily 4/18

No work due to rain and snow mix weather.

Friday, April 15, 2011

Daily 4/15

24" storm pipe installation continues.

Thursday, April 14, 2011

Daily 4/14

Pipe installation continues.
Road within the airport property is now open. The section removed will be replaced with asphalt when Trade dr is to be asphalted.



Wednesday, April 13, 2011

Daily 4/13

Peek's on site to remove trees and stumps.

Daily 4/13

Str 18 in place and installing more pipe.

Tuesday, April 12, 2011

Daily 4/12

Pipe installation continues. Installed first manhole.

Monday, April 11, 2011

Daily 4/11

Steps have been pulled out of structures.
Crews are continuing laying pipe in the airport property.
Silt fence was installed today.

Thursday, April 7, 2011

Daily 4/7

24" Storm continues to be installed.
Clearing of road starts.
Found steps are in structures, told Thad and Ian to pull NOT cut out steps.

Wednesday, April 6, 2011

Daily 4/6

Took the fence down. Stock piling material on site.

Tuesday, April 5, 2011

Daily 4/5

Met on sit to discuss tree removal and other things.
Brian McMillen Airport Authority
Dustin Peek Peek's Tree Experts
Thad B. C & E

Mike