Tuesday, September 27, 2011

North approach

Pictures show the North approach for the St Joseph County Ducomb
Center. The contractor Ancon did the work of the curb cut along with
the concrete pad and walks. They also poured half of the approach on
the East side.

Tuesday, September 6, 2011

Final Documents

Approved Pay Estimate 4, 5, and CO 1

Pay Estimate 4 = $124,905.88
Pay Estimate 5 = $18,101.60
Final Change Order = $2,750.36 (Increase 0.77%)
Final Cost = $362,031.93

Monday, August 29, 2011

Approach issue

Resolved the issue with the concrete bus pad being to high. The section detail didn't have an exact station for the concrete pad so the elevation of the pad was off the approach. But as the drive was built to the plans, the building of the parking lot has the drive a foot lower that what C&E built. Instead of the contractor at the Juvenile center charging the city to put back the approach lower, an agreement was made that C&E will remove the pad and saw cut and remove the East half of the approach and the contractor at the Juvenile center will grade and install the pad and approach. 

Tuesday, August 23, 2011

Payroll Issue

While checking payrolls the subcontractors (Walsh & Kelly, Slusser's, and Mike's Fencing) have not paid the minimum wage rate amount for the project. Contacted Donna at C&E and informed her of this. She stated that she will contact the sub and ask them to fix the issue and pay restitution.

Wednesday, August 10, 2011

Payroll 1, 2, 3, 4, 5, 6, & 7

Approved payrolls (Michiana Contracting) for the weeks ending:
6/19/11
6/24/11
7/1/11
7/8/11
7/17/11
7/22/11
7/29/11

Payrolls 12, 13, 14, 15, 16, 17, & 18

Approved payrolls for the weeks ending in:
6/20/11
6/27/11
7/4/11
7/11/11
7/18/11
7/25/11
8/1/11

Payroll 1

Approved payroll (Peek's Tree Experts) for the week ending in 4/16/11